Board
JOB-2367Paid

EV Charger Install (11 ports) — Eastgate Property Management

Eastgate Property Management · Building B — Maintenance Shop

$5,158
EV Charger Install

Scope of work

Add EV charging capacity including panel work and conduit run. All work per NEC and local amendments.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material14/2 NM-B w/ Ground — 250 ft coil2 coil$128.13$256.26
Material20A Double-Pole Breaker7 ea$36.97$258.79
Material10 AWG THHN Copper, Red — 500 ft spool1 spool$305.45$305.45
Material12 AWG THHN Copper, White — 500 ft spool2 spool$200.81$401.62
LaborElectrical labour — ev charger install33.4 hr$117.84$3,935.97
Total$5,158.09

Customer

Open
Eastgate Property Management
Emmett Alderman
Maintenance Coordinator
308 Copperfield Row
Safety Harbor, FL 34425
Assigned crew
Crew 3 — Residential

Timeline

  1. Lead created
    Oct 25, 2022
  2. Won
    Nov 14, 2022
  3. Scheduled
    Dec 2, 2022
  4. Completed
    Dec 9, 2022